Adamian Renovation: November 2026 Highlights
November 23, 2026
Dear Bentley community,
As everyone gets ready to head home for Thanksgiving break, work at Adamian is heating up. Over the coming weeks, the building will continue its transformation as more of the interior finishes are installed and individual spaces begin to look and feel like the finished Adamian Academic Center.
Here are some of the key project highlights happening in November.
Construction progress:
- The building is now approximately 85–90% weather-tight, so most of the exterior is enclosed and protected from the elements.
- Installation of the exterior façade (see the image below) and the windows are nearing completion.
- Crews are prioritizing outdoor work to complete as much as possible before winter weather sets in.
- Interior finishes are progressing, with bathroom floor tiling underway and painting and flooring being installed in office areas.
Upcoming phases:
- Complete the remaining exterior work to make the building fully weather-tight and allow indoor temperatures to be maintained for finishing work.
- Bring in custom cabinetry, woodwork and other wall and flooring materials so they can adjust to the building's indoor temperature and humidity before installation.
- Complete the mechanical, electrical and plumbing work in the café so walls can be closed and interior finishes can begin.
Install ceiling grids, which will support lighting fixtures and heating and cooling vents.
Here are some recent pictures from the site:

The Adamian exterior is looking more and more like the architectural renderings.

A beautiful drone's eye view of Adamian in late autumn.

Light streams in at the Falcon Forum.

Myers Studio is one of the remaining areas that still has open ceilings.
You can also find project information on the Adamian project webpage. If you have questions, please contact Jon Nattinville in Facilities at jnattinville@bentley.edu.