Dear Bentley community,

The power is on in Adamian! This is a major step forward in our renovation project as we shift from completing the foundational, structural work to installing the interior finishes that will bring the building to life. This winter, crews can look forward to working mostly in enclosed, heated spaces.

Here are key project highlights this month:

Construction progress:

  • Permanent power is connected to the building.
  • Nearly 90% of the windows are installed.
  • The exterior terracotta panels are in place, giving the building more of its finished look.
  • Finish work has begun in some areas, including floor tile installation in the bathrooms.
  • Installation of the mechanical, electrical and plumbing systems is nearing completion.

Drywall installation continues as interior spaces begin to take shape.

Upcoming phases: 

  • The next major milestone is to make the building weather-tight by mid-November, with exterior glass installation continuing.
  • Heat will be turned on to maintain temperatures needed for interior finish work.
  • Painting, carpeting in offices and bathroom tile installation will continue.
     

Here are some recent pictures from the site: 

Exterior of Adamian building under construction in October 2026

 

 

 

 

 

 

 

 

With the Boston skyline in the background, Adamian is looking less like a construction site and more like a view of Bentley's future.

Interior of Wilder Auditorium under construction in October 2026

 

 

 

 

 

 

 

 

New ductwork above Wilder Auditorium.

Interior of Falcon Forum under construction in October 2026


 

 

 

 

 

 

 


A "Skyjack" platform lift makes it easier for workers to reach the multi-level heights of the Falcon Forum. 

Office hallway in Adamian under construction in October 2026

 

 

 

 

 

 

 

 

With the power now on, we can start to envision what going to office hours will look like.

You can also find project information on the Adamian project webpage. If you have questions, please contact Jon Nattinville in Facilities at jnattinville@bentley.edu.

Stay tuned for another progress update next month.